| MUZZI MARSH
Muzzi Marsh is one of the earliest marsh restorations on San Francisco Bay. It was begun in 1974 on 130 acres in Corte Madera, Marin County, between Highway 101 and the Bay, with commercial development beside it and residential neighborhoods overlooking it. It was undertaken to mitigate wetland damage from the dredging of Corte Madera Creek to make a channel for the Golden Gate Bridge Districts ferry terminal in the adjacent town of Larkspur.
Muzzi had hard beginnings. Two opposing techniques were applied: one favored natures way, the other, engineerings way. To complicate things, the Bridge District decided to dispose of dredge spoils on the new site, and that caused trouble later.
The first technique was simple. Our idea was to breach the dike to bring the tide in, and then let nature take its course, explained botanist Phyllis Faber, an environmental consultant to the Bridge District. Nature tried hardwetland plants were sprouting on what had been a barren wastelandbut not hard enough for some observers. Among these were homeowners who looked down on the site and did not see the lush wetland they had expected to see.
The District received complaints, and the upshot, of course, was a committee. We formed a committee of all the regulatory agencies plus the City and the Marin Conservation League, said Gene Rexrode, then project engineer for the District, now retired. Fifteen people. It took an enormous amount of time to get them to agree on what to do. We knew there was a problemportions of the land (where the dredged materials had been put) were too high. The tide wasnt getting there, and vegetation wouldnt grow. Finally, the committee decided to try engineering. New breaches and channels were dredged to increase tidal flow.
Now, 25 years after restoration began, how is Muzzi doing? Stupendous! Faber said, as she surveyed acres of pickleweed and native cordgrass with gum plant scattered throughout. The marsh is frequented by many birds, among them 15 nesting pairs of endangered clapper rail, as well as the salt marsh harvest mouse (whether its nesting is not known).
Did the engineering help speed the marshs recovery? Faber, who is monitoring progress for BCDC, said, The new channels have improved tidal flow, but they were inappropriate in size. Now natural meandering channels are forming within them and correcting them. Chalk one up for Mother Nature.
Would these results have been achieved had the first plan been let be? Oh yes, said Faber, though more slowly. People dont realize how much time it takes for a marsh to restore.
Fred Botti, associate wildlife biologist with the Department of Fish and Game in the Bay Region, said, Muzzi Marsh is coming along very well. Even though a restoration may not meet full expectations, that doesnt mean its a failure. Its arrogant to think we can go in and do a certain kind of marsh. We should just let it develop naturally.
So the lesson here is that marsh restoration requires patience and a willingness to accept results that might differ from those intended.
BATIQUITOS LAGOON
Batiquitos Lagoon, a 160-acre tidal marsh restoration in Carlsbad, San Diego County, was begun in 1994 as mitigation for an expansion of Los Angeles Harbor that required extensive dredging and filling.
The lagoon lies between low bluffs, farm land, grasslands, and the ocean. A sub-division of luxurious homes views it from above. Two highway bridges and a railroad line span it at the ocean inlet.
The site was chosen by a team of wetland regulators and advisors, and they took some brickbats: Batiquitos is 50 miles from Los Angeles Harbor because an assiduous search failed to turn up a suitable site nearby. Also, it is a different habitat from what the harbor work destroyed.
Joy Zedler, then a professor of biology at San Diego State University, deplored the loss of 400 acres of shallow bay habitat that Batiquitos would not replace. The effect upon the region is a net loss, she wrote in the winter 1987 edition of this magazine.
There was no net loss of in-kind habitat values, countered Jack Fancher, a coastal restoration specialist with the U.S. Fish and Wildlife Service, which played a major role in preparing the restoration plan. Eelgrass and pickleweed are going gangbusters. And snowy plover and least tern are nesting on five islands. The goal of the project was not to replace the shallow bay habitat, but to provide habitat for the same species. This was done.
Restoring tidal flow to Batiquitos was a daunting task. The ocean inlet, long sealed off, had to be recreated. The highway bridges and the railroad right-of-way had to be reconstructed to let the tide in. The engineers used state-of-the-art models, but they dont always work, said Fancher. A sand bar has appeared at the inlet. We may have to dredge more often.
To this writer, a recent visitor, the lagoon looked very good. It exhibited a sequence of mud flat, salt marsh, shallow ponds, nesting islands. Tides are flowing, and there are many birdsavocets, egrets, blue herons, terns, widgeons, pintails, ruddy ducks, and others. Merkel and Associates, the firm monitoring restoration progress, reported in 1997 that the count of bird species had jumped from 94 before construction to 127. Fish species, particularly ocean species, were also increasing. Clearly, Batiquitos has profited from the increasing store of scientific knowledge about wetlands.
REVELATIONS
Were Bracut Marsh and Muzzi Marsh and Batiquitos Lagoon successes or failures? That is in the eye of the beholder, said Josselyn. Environmentalists are inclined to say if every function is not performed perfectly, its a failure. Josselyn measures success function by function. Is vegetation cover ample? Are birds nesting? Is tidal action adequate? Do the results meet the goals set forth in the project design? If 60 percent perform, thats success, he said. If 35 percent, partial success. If five percent, failure.
By this measure Bracut and Muzzi and Batiquitos are not failures. They have not sunk to that dreadful five percent. Theyre not perfect recreations of naturethat doesnt happenbut theyre functioning wetlands.
But the process needs considerable improvement, particularly as regards monitoring and enforcement of permit requirements. These are all too often absent, said Paul Jones, San Francisco North Bay coordinator for the EPA: The agencies only do the front endthe permits. [For want of staff], the back endmonitoring for compliance with permit requirementsgets shortchanged.
Jones, in collaboration with others, has devised a monitoring program for north San Francisco Bay, which could become a model for elsewhere. It will assess wetland failures and successes, and seek ways to improve the science of wetland restoration. That effort may ease some of the wetland controversies, but not all. There remains the question of whether wetlands that retain habitat values should ever be destroyed. Some environmentalists say no, never. Others accept public but not private developments. In practice, that distinction is hard to make. The Coastal Commission allows private industries that are coastal-dependent; BCDC allows private businesses that are water-oriented and serve the public. Its a matter of interpretation on both sides.
Will Travis, executive director of BCDC, offered this comment: There are two ways to look at mitigation. One, there are vast areas in the Bay Area with a potential to be restored. It would take 50 years to buy them all. Bringing in private capital makes it faster. Two, the loss of even a square inch of wetland is a defeat. So hold them all in reserve until theres enough money to restore them all.
Its unrealistic to expect that all remaining degraded wetlands in the Bay Area can be restored. The San Francisco Bay Area Wetlands Ecosystem Goals Project, authors of the impressive Baylands Ecosystem Habitat Goals, acknowledges that such a visionary goal may be beyond reach. Certain considerationseconomic constraints, landowner desires, zoning, and societal interestsmight make it difficult or impossible to implement [all the goals set in the report], they wrote. Add to these the high cost of restoration, which, for a hypothetical medium-sized wetland with moderate site constraints, was estimated at $7 million.
It seems inevitable that some wetlands will be lost to development. And what of those remaining? For want of funding, many could languish, unrestored and unproductive, for years. Or they could be restored as compensation for those lost, thus providing more healthy marshes than would otherwise be realized. That is what mitigation is meant to do. A wetland restored as mitigation is, so to speak, a wetland bird in the hand. 
Margaret Azevedo served on the North Central Coast Regional Coastal Commission from 1972 to 1976 and has been a member of the Coastal Conservancy since it was established in 1976. |